Comcast

Proffer amendment filed for increased FAR. Approval est. Q3/2023. Located within Data Center Overlay

ARC

Permanent power will require a
new substation to be built, which
will be 36-48 months.

Starkey

Incentive package from Township and State, preliminary Geotech, “shovel ready” site. Phase 1 environmental complete.

Hunter Trust

Site plan has been submitted. Property is located within the Data Center Overlay Can build up to 75 ft